Hammersmith Bridge Road - Highway Improvements



Hammersmith Bridge is to be closed to all vehicle traffic from 5am on Saturday until Monday mornings each weekend until Monday, March 15 and the bridge will also be closed throughout the school half term break between Saturday, February 13 and Monday, February 22.

The bridge will remain open to pedestrians and cyclists.

THE PLANNED BRIDGE CLOSURE DATES ARE AS FOLLOWS:

1. Weekend closure - Closed from 8.00pm Friday 22 January 2010 - reopened from 5.00am Monday 25 January 2010
2. Weekend closure - Closed from 8.00pm Friday 29 January 2010 - reopened from 5.00am Monday 1 February 2010
3. Weekend closure - Closed from 8.00pm Friday 5 February 2010 - reopened from 5.00am Monday 8 February 2010
4. School Half Term Week Closure including 2 weekend closures either side of the Half Term Week - Closed from 8.00pm Friday 12 February - reopened from 5.00am Monday 22 February 2010
5. Weekend closure - Closed from 8.00pm Friday 26 February 2010 - reopened from 5.00am Monday 1 March 2010
6. Weekend closure Closed from 8.00pm Friday 5 March 2010 - reopened from 5.00am Monday 8 March 2010
7. Weekend closure - Closed from 8.00pm Friday 12 March 2010 - reopened from 5.00am Monday 15 March 2010

PLEASE NOTE: The above times and closure dates are subject to change if the council deems it necessary as a result of unforeseen circumstances beyond their control, which may impact greatly on the road network.